CR 400 Road Improvements

Project Description

This project aims to reconstruct E. CR 400 N. between Ronald Reagan Parkway and an approximate distance of 1500 feet west of Ronald Reagan Parkway. The plan includes replacing the current box culvert under CR 400 N. Additionally, the project will add a dedicated right turn lane towards the southbound on Ronald Reagan Parkway at CR 400 N. All the associated work with this addition will also be included in the project.

Schedule

Project is currently in the Construction phase. Dates are subject to change due to supply change and weather delays. 

  • March 2024 - Construction Start
  • June 2024 - Construction Completion
  • July 2024 - Project Close-out

Funding

The project is funded in coordination with the developer.